Punjab RERA orders Rs 25L payout for delayed possession, sets key precedent
Mohali: In a significant ruling, the Punjab Real Estate Regulatory Authority (RERA) has directed a real estate promoter to pay around Rs 25 lakh as delay interest to homebuyers, holding that project timelines must be counted from the initial booking date rather than the execution of the sale agreement.
The complainants — faculty members of Punjab Engineering College, Sector 12 — had alleged faced delay in possession of their property. The case was argued by advocate M Shahnawaz Khan.
In a key finding, the authority held that where initial booking was made in 2018, the promoter could not defer liability by delaying execution of the agreement, which in this case was signed in Dec 2022 with a possession date of July 31, 2023.
Relying on Supreme Court precedents, RERA ruled that the reasonable period for delivery of possession is capped at three years from the date of booking or advance payment, regardless of when the formal agreement is executed.
The authority quantified the delay interest payable to the complainants at approximately Rs 25 lakh as on the date of the order.
It also rejected the builder’s plea seeking extension on grounds of Covid-19, observing that force majeure provisions cannot be used as blanket protection where delays are attributable to the developer.
Counsel for the complainants said the order reinforces the principle that the rights of homebuyers flow from the date of booking and payment, and not merely from the execution of agreements.
WHY IT MATTERS
Who benefited: PEC faculty members (allottees)
Key ruling: Timeline counts from booking date, not sale agreement
Booking year: 2018 | Agreement signed: Dec 2022
Possession deadline cited: July 31, 2023
Legal takeaway:
Max reasonable delivery period 3 years from booking/payment
Builders cannot defer liability by delaying agreements
Builder’s defence:
Covid force majeure plea rejected
Impact:
Strengthens homebuyers’ rights
Sets precedent against project delays and misuse of timelines
In a key finding, the authority held that where initial booking was made in 2018, the promoter could not defer liability by delaying execution of the agreement, which in this case was signed in Dec 2022 with a possession date of July 31, 2023.
Relying on Supreme Court precedents, RERA ruled that the reasonable period for delivery of possession is capped at three years from the date of booking or advance payment, regardless of when the formal agreement is executed.
The authority quantified the delay interest payable to the complainants at approximately Rs 25 lakh as on the date of the order.
It also rejected the builder’s plea seeking extension on grounds of Covid-19, observing that force majeure provisions cannot be used as blanket protection where delays are attributable to the developer.
Counsel for the complainants said the order reinforces the principle that the rights of homebuyers flow from the date of booking and payment, and not merely from the execution of agreements.
Who benefited: PEC faculty members (allottees)
Key ruling: Timeline counts from booking date, not sale agreement
Booking year: 2018 | Agreement signed: Dec 2022
Possession deadline cited: July 31, 2023
Legal takeaway:
Max reasonable delivery period 3 years from booking/payment
Builders cannot defer liability by delaying agreements
Builder’s defence:
Covid force majeure plea rejected
Impact:
Strengthens homebuyers’ rights
Sets precedent against project delays and misuse of timelines
Comments
Be the first to share a thought and become theFirst Voiceof this News Article
Popular from Business
- Setback for Indian mango exports! Why Japan has stopped imports of Kesar, Alphonso, Langra & other varieties from India
- Bengaluru said Swalpa Adjust Maadi for too long; Casagrand Moondance on Mysore road begs to differ
- Labour codes and nomination processes: What employees need to know about securing their benefits
- Thrice rebuffed for US visa, Sanjay Mehrotra joins Satya Nadella and Sundar Pichai in the trillion-dollar club
- Gold, silver price prediction: Where are gold & silver prices headed in the near future? Check MCX Gold, MCX Silver price outlook
end of article
Trending Stories
- Setback for Indian mango exports! Why Japan has stopped imports of Kesar, Alphonso, Langra & other varieties from India
- Shampoo, sacks and more: How is Middle East conflict making your groceries costlier?
- Bank holiday today: Are banks closed on May 28 for Bakri Eid? Check state-wise list
- Stock market holiday on Bakri Id: Are BSE, NSE closed for trading on May 28?
- 8th Pay Commission: Railway staff body seeks different fitment factors; here are their recommendations on salary hike
- Big milestone! Adani Power overtakes Infosys in market capitalisation; share rallies over 65% year-to-date
- Cabinet approves Rs 25,530 crore scheme to strengthen ration distribution system till 2031
Photostories
- 10 toxic habits you think are normal, but they're holding you back
- Indoor plants that you can grow without soil
- BTS’ Jung Kook launches first motorcycle-inspired clothing line with Calvin Klein – Everything to know about this partnership
- India’s hidden wine regions beyond Nashik
- Why atta dough turns dry in the fridge and 3 easy ways to retain its moisture
- 2 Misunderstood traits of high intelligence
- Who is Pankaj Bhadouria? Celebrity Chef and MasterChef India season 1 Winner diagnosed with breast cancer
- 5 art villages of india where art has been passed down from generations and is a way of life
- Can diabetics eat mangoes? Experts say yes, but only if you follow these rules
- 5 lesser-visited UNESCO World Heritage Sites in India travellers should explore
Up Next
Follow Us On Social Media