Western Railway has floated an Rs 86.5-crore civil works tender for the proposed Harbour Line extension between Goregaon and Borivli under MUTP-3A. (Representational image)

WR invites bids for key infrastructure works
2/8

WR invites bids for key infrastructure works

The tender package includes earthwork, bridge construction and allied infrastructure works for the proposed Harbour Line extension between Goregaon and Borivli. (Representational image)

Goregaon-Borivli Harbour Line extension estimated at Rs 898 crore
3/8

Goregaon-Borivli Harbour Line extension estimated at Rs 898 crore

The project cost includes Rs 728 crore for civil engineering works, Rs 88 crore for electrical works and Rs 82 crore for signalling and telecom. (Representational image)

Project includes construction of 18 bridges
4/8

Project includes construction of 18 bridges

Authorities plan to build two major bridges and 16 minor bridges as part of the proposed Harbour Line extension between Goregaon and Borivli. (Representational image)

Land acquisition remains a key challenge
5/8

Land acquisition remains a key challenge

The project requires 3,688 square metres of land, including 3,389 square metres of private land and 299 square metres of government land. (Representational image)

Rehabilitation process underway for PAPs
6/8

Rehabilitation process underway for PAPs

Authorities identified 520 PAPs on railway land. Rehabilitation units have been allotted to 178 PAPs, while 141 PAPs are affected on private land. (Representational image)

Key challenges remain for Harbour Line extension
7/8

Key challenges remain for Harbour Line extension

Completion of land acquisition, rehabilitation of remaining PAPs, removal of encroachments and approval of pending bridge drawings remain major challenges. (Representational image)

Latest tender floated on May 27
8/8

Latest tender floated on May 27

The Rs 86.51-crore tender covers rail formation, bridges, side drains, retaining structures and boundary walls for the Harbour Line extension project. (Representational image)